A can complete a certain work in 30 days. B is 25% more efficient than A and C is 20% more efficient than B. They all worked together for 3 days. B alone can complete the remaining work in:
A. 12 days
B. 20 days
C. 18 days
D. 15 days
SSC CGL 2019 Tier 1 4 March 2020 Shift 1
Solution:
In this question from Time and Work,
Let us see the shortcut method first:
Let us assume the efficiency of A be 4 (it means A can do 4 units of work in a day)
Therefore, the efficiency of B will be = 125% of the efficiency of A = 5 (it means B can do 5 units of work in a day)
Therefore, the efficiency of C will be = 120% of the efficiency of B = 6 (it means B can do 6 units of work in a day)
Total units of work = 30 x 4 = 120 units
Total work done by A, B and C in 3 days = (4 + 5 + 6) x 3 = 45 units
Remaining work = 120 - 45 = 75 units
The number of days required by B to complete the remaining work = 75/5 = 15 days.
Hence, (D) is the correct answer.
Let us see the basic method:
The efficiency of A = One day work of A = 1/30
The Efficiency of B = One day work of B = 1/30 + (25/100) x (1/30) = 1/30 + 1/120 = 1/24
The Efficiency of C = One day work of C = 1/24 + (20/100) x (1/24) = 1/24 + 1/120 = 1/20
Let the remaining work completed by B in x days
As per the question, we get
(1/30 + 1/24 + 1/20) x 3 + (1/24)x = 1
x/24 = 1 - 3/30 - 3/24 - 3/20
x/24 = (120 - 12 - 15 - 18)/120
x/24 = 75/120
x = (75 x 24)/120
x = 15
Hence, (D) is the correct answer.
Comments
Post a Comment